Date: 2015
Supply of ProTek® Jet Fire & Blast Protection Fire Enclosure for Hang-off & Cable Penetration Modifications at Åsgard B
Products commissioned: ProTek® Structural Composite Enclosures
Client: Statoil/Aker Solutions
Location: Haltenbank in the Norwegian Sea
Customer requirement/ problem
- Jet Fire and Blast protection required for Riser Hang-off
- Modifications of Existing Fire Enclosures required for newly installed platform equipment
- Cable Penetration Modifications and Replacement Moulded Laminate sections to accommodate a new locking ring arrangement
- Delivery to suit platform availability constraints
- Jet Fire and Blast protection required for the equipment
- Minimum weight to be added to the platforms
- Maintenance and personnel access to protected equipment required
- Penetration detail requirements for ancillary equipment
- Enclosure delivery to suit activities at site and to meet commissioning targets
- To meet Statoil HSE requirements throughout project lifecycle
ProTek® Solution
- Jet fire and blast protection enclosures to protect Riser Hang-off
- Integrated fire resistant instrument tubing and cable penetration plate details for new and Existing Enclosures
- Earthing details to comply with ATEX directive
- Minimum design life of 20 years
- Lightweight enclosure incorporates ProTek® structural composite panels and high strength bolted 316 l stainless steel frame
- 3D models developed to ensure good fit up and determine routing of services
- All equipment assembled at SCS premises before shipping and commissioning at Customer’s TLP
- Rapid installation by local personnel with SCS training and supervision support
- Independent third party certification for all enclosures